|
Consent AdjudicationConsent
Orders and Agreements
EY
2001
Introduction:
The
Harrisburg Field Office conducted a review of the Pennsylvania
Department of Environmental Protection=s (PADEP) use of settlement
agreements for third-party reclamation of bond forfeited permits with
long-term water pollution. The purpose of this study was to assess how
CO&As for third-party reclamation on forfeited permits address
existing pollutional discharges. In addition, the study looked at how
these agreements dealt with long-term success of reclamation performed
by third parties. Summary
Findings:
Data
Presentation and Discussion:
This
CO&A study of third-party reclamation on forfeited permits with
long-term pollutional discharges (AMD) began in Evaluation Year 2000,
and was completed early in Evaluation Year 2001. For the study, OSM
reviewed eleven CO&As covering twenty-three bond forfeited permits.
Of the 23 permits reviewed, 22 had at least one pollutional discharge at
the time of forfeiture. The discharge on the remaining permit met
effluent limits at the time of the field inspection. PADEP
had successfully accomplished land reclamation on 22 of the 23
third-party reclamation sites reviewed. This includes returning the site
to the approximately original contour, elimination of all highwalls, and
successful revegetation. On the remaining permit, PADEP had scheduled
land reclamation to begin in the near future. PADEP
effectively addressed serious long-term water pollution issues on the
permits reviewed. One of the permits reviewed met effluent limits; two
others had ceased to flow; seven were receiving some form of passive
treatment; and the remaining 13 permits, which had no treatment
occurring, were characterized as having low-flow discharges with no or
minimal offsite impacts. On the 7 discharges with passive treatment, no
provision had been made with the third-party for long-term monitoring or
maintenance of the treatment systems. However, PADEP plans to address
any long-term programmatic responsibility for discharges on primacy
forfeitures by several means. These include; excess funds from the
alternative bonding system, Title IV 10% set-aside funding approved for
qualified hydrologic units, Title IV funding in cases involving
insolvent sureties, remining by qualified operators, and
reclamation-in-lieu of civil penalties. In
addition, for the CO&As reviewed where surety companies were
performing the reclamation, the responsibility for long-term success of
revegetation was assumed by PADEP. PADEP has received $5.5 million from
the legislature to address revegetation failure and to insure long-term
success of reclamation on forfeited sites. Background:
One of the means
employed by PADEP to achieve successful reclamation of bond-forfeited
sites is settlement agreements with third parties. The objective of
these settlement agreements, which are frequently negotiated with surety
companies, is to accomplish reclamation of the forfeited site at a cost
savings to the state’s alternative bonding system. In these
agreements, PADEP completes the forfeiture action, but forgoes
collection of part or all of the bond in exchange for the third party
performing full reclamation of the site. In such cases, the third party
essentially acts as a contractor performing the reclamation after
forfeiture. In the past, OSM has observed that PADEP’s use of these
settlement agreements has consistently achieved an equal amount of, and
in many cases more, land reclamation than would have been possible using
just the forfeited bond monies. The reclamation plan is accomplished for
land reclamation, but long-term water pollution issues were not always
addressed because of inadequate bond. As a result, receiving streams and
associated watersheds may be impacted when a bond is forfeited.
(Insufficient bond to address long-term treatment of pollutional
discharges is an issue shared by most coal producing states.) PADEP is
planning to address long-term treatment of forfeiture discharges through
several program mechanisms described in the following section of this
report. Where applicable, the alternative bonding system fund (bond
pool) provides funding for any additional reseeding and planting needed
to insure long-term revegetation success. Third-party
settlement agreements take two forms: Consent Adjudications (CA) and
Consent Order and Agreements (CO&A). CA’s are agreements approved
by the Environmental Hearing Board (EHB) and published in the
Pennsylvania Bulletin with a 30-day comment period. EHB approval means
that the agreement is not contrary to law, and that all comments were
considered. CO&As, on the other hand, are not submitted to the EHB
for approval; they are generally used to address matters that have not
been appealed. CO&As are also used to establish agreements for
reclamation in-lieu-of cash payments for civil penalty debt. For
simplification, this report will refer to both types of agreements as
CO&As. Methodology:
The
sample population for this study was all CO&As with long-term
pollutional discharges identified during a separate study of CO&As
related to post bond forfeiture third-party reclamation of primacy
permits. The Field Office's findings for each CO&A and the
underlying sample permits are based on review of the agreement, as well
as, file reviews and onsite inspections of the permits. OSM and PADEP
personnel jointly conducted the majority of the inspections.
|